Rajasthan Chief Secretary V. Srinivas reviewed the progress of construction work of the Kota-Bundi New Greenfield Airport at the Government Secretariat. He directed that all works be operated simultaneously and completed within the stipulated timeframe.
According to a government release, the construction work of the Kota-Bundi Greenfield Airport is proposed to be completed by October 4, 2027. The Chief Secretary told officials that infrastructure such as the runway, terminal building and ATC tower should be developed simultaneously so that the work can be completed on time.
New airport will be equipped with modern facilities
A passenger terminal building spanning an area of 20,000 square meters will be constructed at this airport, with an annual passenger capacity of 20 lakh. For the convenience of passengers, 14 check-in counters and 9 self-check-in kiosks will be established here.
- The airport will feature automatic baggage handling systems and baggage claim carousel facilities.
- A G+3 storey technical block and fire station are being constructed for the ATC system.
- A solar plant with a capacity of 1 megawatt will be installed to meet energy requirements.
- A 6-lane approach road and parking will be constructed for passenger movement.